The WORKDAY function can be used to calculate the end date or start date of a project for a given number of business days. The number of business days cannot include weekend days. Specific holidays can also be omitted.
The syntax for the WORKDAY function is:
= WORKDAY ( Start_date , Days , Holidays )
Start_date - the start date of the project or time period in question.
Days - the number of days work on the project occurred after the Start_date.
Holidays - can be used to exclude one or more dates from the total number of working days (optional).
Example: Calculating a Project End Date
For help with this example, see the image above.
- Enter the following data into the appropriate cell:
D1 - Start Date:
D2 - Days:
D3 - Holiday 1:
D4 - Holiday 2:
D5 - End Date:
E1 - 7/6/2009
E2 - 87
E3 - 9/7/2009
E4 - 10/12/2009
Note: If the dates in cells E1, E3, and E4 do not appear correct, check to see that these cells are formatted for dates.
- Click on cell E5 - the location where the results will be displayed.
- Click on the Formulas tab.
- Choose Date and Time functions > WORKDAY from the ribbon to bring up the
function's dialog box.
- Click on the Start_date line in the dialog box.
- Click on cell E1 in the spreadsheet to enter that cell reference into the dialog box as the Start_date argument.
- Click on the Days line in the dialog box.
- Click on cell E2 in the spreadsheet to enter that cell reference into the dialog box as the Days argument.
- Click on the Holidays line in the dialog box.
- Drag select cells E3 and E4 in the spreadsheet to enter these cell references into the dialog box as the Holidays argument.
- Click OK in the dialog box.
- The end date for the project - 11/6/2009 appears in cell E5.
- When you click on cell E5 the complete function
= WORKDAY ( E1 , E2 , E3 : E4 ) appears in the formula bar above the worksheet.
Note: The WORKDAY function can also be used to find a date in the past - such as the day work began on a project. To do so enter a negative number for the Days argument and use the project's end date for the start_date argument.